ISS Ltd were contracted to carry out the upgrade of this bridge to allow for the crossing of the 500 tonne turbines for the E3P Project at the Genesis Energy Power Station in Huntly. ISS Ltd carried out all the Site Fabrication and Welding of the new arches and the under bridge strengthening. ISS Ltd designed the system of installing the new arches 68 tonne arches over the existing arches they then proceeded to dismantle the old arches. A challenging project because this bridge is the only access point to the town center, so this rebuild took place with only 7 after hours road closures. Thus minimising
any disruption to the public.
In this photo you can see the old arches still in place under the new.
.
ISS Ltd were awarded part of the contract to supply Scaffolders, Riggers, Dogmen, Supervisors and Scaffolding Equipment on this project which saw our experienced crews and gear being involved with this project for close to 2 years.
Aerial shot showing the scale of this project. The entire Turbine hall was erected by the various erection crews on site.